In this topic you will
find the most common Questions and the Model Answers that you may expose to in
your Interview for a Planning Engineer Position.
Question No.1:
What is a constraint in primavera?
Constrains in primavera
is to fix the early or late start or finish dates of an activity as per
following options:
A-Project Must Finish by
B-Mandatory Start / Mandatory Finish
C-Start / Finish On or After
D-Start /Finish On
or Before E-Start / Finish On
F-Expected Finish
what is
the clause to be refereed in FIDIC when there is entitled for extension of time
Clause 20.1, "If
the Contractor considers himself to be entitled to any extension of the Time
for Completion and/or any additional payment, under any Clause of these
Conditions or otherwise in connection with the Contract, the Contractor shall
give notice to the Engineer, describing the event or circumstance giving rise
to the claim. The notice shall be given as soon as practicable, and not later
than 28 days after the Contractor became aware, or should have become aware, of
the event or circumstance".
Question No.3:
What is
the reasonable range of float you assume while checking the look ahead work
activities?
The float range is
varied from a project to another. However, in my opinion 10% of project
duration is the maximum reasonable float for any project.
Question No.4:
What is
the Critical Path? How you identify it and if any activity having negative
slack, how can you adjust the duration?
Critical path is usually
the activities on the longest path with zero float. Any delay on these
activities will lead to delay in project duration. Usually critical activities
are shown in red color or say zero float in columns. For reducing duration you
can adjust it by reducing the duration or changing the relationship between
activities. However, planning engineer should pay attention to maximum
resources (resources constrains) while crashing the critical path.
Negative slack is
usually results from constrains in the activities. Planning Engineer should
follow up the negative float path and find the wrong relationships or
constrains and fix it.
What is the
difference between Planning & Scheduling Engineer?
Planning Engineer can
work along with the project team to develop a complete time schedule including
cost of resources. Planning Engineer can lead the team and influence his/her
point of view.
Scheduling Engineer
can only follow senior planning engineer or project manager instructions to create logic between project activities,
but s/he can't develop the time schedule alone.
Question No.6:
What is the
difference between Retained Logic & Override Logic?
Retained Logic is
Invariably that will produce the longest critical path but if activities have
been progressed out of sequence, there could be some illogical dependencies
remaining, in particular resulting from dependencies with duration.
Progress override
invariably produces a shorter critical path and again there could be some
illogical lack of dependencies resulting from activities having been progressed
out of sequence.
What is the
difference between recovery schedule and revised schedule?
Recovery schedule
keeps the same finish date with some corrective actions to recover the delay
such as add more resources and break down some activities and so on... Revised
schedule we have a new finish date because of claims or adding a new scope of
work (amendment).
Question No.8:
You are
working on a project and somewhere in the middle of the project. The progress
variance was -5% and still you are achieving the contractual completion date.
How is it possible?
Contractor is working on critical
path and delays are on non-critical activities
Question No.9:
How can
you define the Critical Path in primavera? Simply filter the activities with Zero Total Float.
Question No.10:
As a planning
Engineer, "Walk me through a project":
This Project is
"Project Name" and it has a budget of "Project Budget". The
Project started in "Project Start Date" and planned to be finished in
"Project planned finish date". According to the last update date on
"updated date" this project is (ahead/behind) the schedule where the
planned % = X and actual % = Y, therefore the forcast completion date is Z
Question No.11:
How can you
differentiate total float and free float?
Total float
represents the number of days that can be delayed without affecting the
completion of the project, whereas free float determines the number of days
that can be delayed without affecting the successor activity.
Question No.12:
What is Resource
levelling and What is Resource Allocation?
Resource levelling is
the best scenario to excute the works with the availabe resources. In order to
achieve the best scenario, planning engineer could change the activities durations and/or activities dates without affecting
the project overall duration to maintain bes usage of
resources. While Resource allocation is assigning resources to activities,
determine the amount of labor, equipment and money required for any activity.
Question No.13:
If we
increase 2 days to the duration of any activity on critical path that will
increase the duration of project by 2 days?
Yes. It is on the
critical path which means it as Zero Total Float and any increasing in its
duration will affect the duration of project.
Question No.14:
Explain what a good
schedule means?
a) Scheduled activities must reflect the project’s
contract scope of work)
b) Dates must be in accordance with contract.
c) Meets the contractual requirements /milestones.
d) Activity durations are reasonable: activity duration must be calculated based on quantity of
work and resources available to be applied to the work.
e) Activity relationships are all
defined, as review must be take place all relationships have been included and
all are valid and redundancies are eliminated, and no open ended activities
exept the first and last activities.
f) The critical path makes sense
g) It considers procurement and material and equipment deliveries
h) It must be cost and resource loaded
I) Must be accessible in proper format, complete,
clear, and convenient.
j) Specific must tell
about what will done, who will do, when will do, and what cost will need
Question No.15:
How will you make a
manpower loading for your schedule?
Man Power loading is
based in my company productivity rates, we calulate the required man hors for
each B.O.Q item by using this formula :
Required Man Hours = QTY /
(Productivity Rate)
Question No.16:
What
are the involvements of Project Planner and vital Role in Project Management?
Since Planning
Engineer directly involve in project management activities, project leadership
to make decisions concerning the development of plans, and how work process
broken down & the control how it be manage. Track, review, forecast &
give inputs the status of the Project and product. Further more planning
engineer should raise the flage to project team where s/he recognise and
potential risks
Question No.17:
Float belong to the
Owner or the Contractor?
It is a question that
you probably will not find a definite answer for. The significance of the
argument about who owns the float has two folds, first its ability to directly
or indirectly influence the construction methodology and/or sequence once the
project execution has started, and secondly, the potential entitlement of
extension of time (EOT) and the application of liquidated damages (LDs). There
are mainly three views of the matter which are presented hereinafter .
1. The ‘contractor owns the float’ argument -
This is the
traditional view and still has its appeal among many practitioners. This view
implies that the contractor is entitled to utilize float for his own risk
events and recovery rescheduling.
Not so far ago, a
survey in the United Kingdom suggested that 80% of the respondents assumed that
the contractor owns the float; not surprisingly, the majority of those
respondents were contractors .
2. The client owns the float argument
This is just the
opposite of the view above, the proponents of this view argue that the client
has paid for the project and the program is one
of the tools to
manage the project and monitor progress, therefore, the client should be able
to control the float to reduce costs and control progress, especially when the
program is a contractual requirement
in which the contractor has
developed it for the client’s benefit .
3. The ‘project owns the float’ argument
This view basically
says float is owned by neither the contractor nor the owner. The project owns
the float which means “float is not for the exclusive use of any of the parties
and it serves whoever needs it first” as long as it is used in good faith.
Question No.18:
What
are the methods of calculating EV (earned value)? 1-Updating actual cost of
activities
2-Updating
the actual budgeted units of activities
3-Updating the actual resources comparing to budgeted ones
Question No.19:
What is the
difference between recovery plan and revised plan?
Recovery plan is made
with acceleration to remain within contractual completion date but revised
plans accounts for change order which may or may not be within contractual
dates
Question No.20:
If the
Project Total Float shows negative, does it always follow that the Performance
% Complete is less than Schedule % Complete?
No. Performance %
Complete has nothing to do with the network logic or the critical path. It is
possible that certain activities with high budgeted value might have been
progressed better than plan but other activities that has less value are the
ones driving the critical path and delays the project completion date.
Question No.21:
How to calculate
budget man-hours?
In order to calculate
budget man-hour you must have the budget quantity for each activity, from that
and through the standard man-hour, convert the quantity into man-hours based on
organization productivity rates, the total of these man-hours will be the
budget man-hours.
Question No.22:
What do you mean by
SDK , & what is its usage in Primavera?
Its stand for "
Software Development Kit " it is used in Primavera to export quickly all
the resources , cost etc. from Excel to Primavera. It is a powerful tool but it
has some limitations with Excel version, i.e should 32 not 64.
Question No.23:
How do you start
planning without any information on hand?
Gather the necessary
Materials, such as the Scope requirements, project start and finish dates and
any documents needed to produce project objective
Question No.24:
What is redundant
logic?
It means that if
successor of A is linked to B and B is linked to C Also Successor of A linked
to C then the link between A to C is called redundancy.
Question No.25:
Is Quality and
Grade are same thing?
No, there is
difference, Quality is the performance of the requirements and fitness to use,
Grade is a matter of different technical characteristic.
Question No.26:
Define
the main responsibilities of the planning engineer in each phase of the
project's lifecycle. Please state clearly which information/data you would need
from the Project Manager/Project management team in order to fulfill your task
as a planner.
This question is tricky because it tests your understanding of the whole planning process throughout the project's different phases. Moreover, you should fully understand the specifications and legal documents related to the particular project in question. However, you will not find it difficult to answer this question if you have been involved in the responsibility of only one completed project from inception to hand over.
Question No.27:
What are the
monitoring skills?
Ability to sort data,
Checking authenticity of data, Analyze and Predict data, Generate Reports.
Question No.28:
Could
you chase Project Managers for information's and not just be a keyboard Junkie?
An answer for this
question could be that I have developed very good interpersonal and communication
skill which accords me the ability to politely yet consistently pull for the
needed answers I require to get my own side of the job going and yet
maintaining a healthy rapport within My team of busy PM's.
Question No.29:
What is the best
software for planning?
No software for
planning, it is only for scheduling, the planning process only done in brain.
However, oracle primavera is the best planning tool that helps to create time
schedules.
Question No.30:
What
would you submit if your consultant / client asks you to submit a matrix
report?
It is an incomplete
request. I must know which matrix do you need, resource matrix, cost matrix,
authorities matrix, engineering/procurement matrix etc. else that would be a
wide report containing more than 50 columns of P6.
Mention
4 reasons cause -ve float in primavera: o
Using project must finish by
o Using Constraints
o Using different calendar in one project
o Using relationships with other project
Question No.32:
What is the
difference between Float and Slack?
There is no
difference between float and Slack. It is two different words of same meaning.
Question No.33:
What is the
difference between negative lag & lead?
There is no difference. It is two
different words of same meaning.
Question No.34:
How do you explain
project delay if earned value is more than planned value?
The contractor has
performed better in areas which are not on longest path "The Critical
Path". In another words, the contractor excuted the right quantity in the
wrong place.
Question No.35:
How are early and
late dates determined?
Early Dates in a
network is determined by Forward Calculations And late dates is determined by
backward Calculations.
What are three
methods of measuring project progress?
Key Performance Indicators
"KPI's", Cost Performance Index "CPI", Schedule Performance
Index "SPI".
Question No.37:
What is the best
way to be professional planning engineer?
Understand the
project management concepts, tools, and techniques. -Practice doing real
projects and get comments/review from expets. -Continous improvement by
learning new tools that would help to increase the accuracy of decrease the
time required for tasks.
Question No.38:
What are SV and CV?
Schedule Variance
(SV) & Cost Variance (CV) in Project Cost Management. Schedule Variance and
Cost Variance are two important parameters in earned value management which
help you analyze the project's progress. Schedule variance (SV)
= Earned value (EV) –
Planned value (PV) Cost variance (CV) = Earned value (EV) – Actual cost (AC)
Question No.39:
What's the way to
resolve the delay in project time?
Fast Track: Reduce
activities duration, resequence, reschedule without affecting the project total
duration, fast tracking has a problem regarding the quality issues if it is
applied in a wrong way.
Crashing: Reduces
activities durations, resequence, reschule but with additional cost to achieve
better results. this additional costs could be:
-Acceleration Costs to
subcontractors.
-Bonus.
-Additional costs
result from less productivity due to increasing the manpower in workplace.
If
Budgeted cost of works is more than actual cost of works, how do you consider
the performance of Project? Optimum, Bad or Good?
Good. Since we are
spending less money than planned, But we also need to check if we are on
schedule or not.
Question No.41:
What is Project
Management?
Project management is
the application of processes, methods, knowledge, skills and experience to
achieve the project objectives. General. A project is a unique, transient
endeavor, undertaken to achieve planned objectives, which could be defined in
terms of outputs, outcomes or benefits.
Question No.42:
What does it mean
if "SPI" greater, lesser or equal to one?
SPI greater than one
means ahead of schedule, less than one means behind the schedule & equal to
one means as per schedule.
Question No.43:
Could we have more
than one critical path?
Critical path is a
dynamic path where it could be changed everytime we update the schedule, change
durations, or relationships. However, the critical path of a project is one
path that could have too many activities underneath. Therefore, the project has
only one criitical path.
Question No.44:
Scope is known
partially, then how to plan for future?
Through the life of
the project as more information is available more work to be planned called
agile management. Accordingly, we can use agile management to plan the known
part of the project only and keep the scope of work until we have more
information about it.
What is
concurrent delay? Concurrent
delays has two meanings:
o When two events of delay on
critical path are occurring at the same time, one affecting activities on
Contractor's risk and the other affecting activities on Employer's risk.
o OR two or more events of delay on
project critical path that belongs to one only of these parties contractor or
client .
Question No.46:
What is a Baseline?
Baseline is the value
or condition against which all future measurements will be compared. The
baseline is a point of reference. In project management there are three
baselines – schedule baseline, cost baseline and scope baseline.
Question No.47:
What is the
Difference between Bar chart & Network Diagram?
Bar charts and
network diagrams are used to display visually the complexities and dependencies
of project work. Network diagrams display the project work as linkages through
the chronological flow of work from start to finish. Gantt charts visually
display primarily the work breakdown and the associated durations. Both charts
graphically show work breakdowns, enabling managers and workers to easily
identify conflicts, co-dependencies and determine the effect of change in the
system
Question No.48:
What is Thresholds
in project Management?
It is the project
management technique in which lower and upper values of a parameter are
specified against which project data can be evaluated and monitored. It could
be applied on WBS level as well as activity level.
What is difference
between crashing and fast tracking?
There are basically
two techniques that can be used to shorten the project duration while
maintaining the project scope. These techniques are fast tracking and crashing.
Crashing is the
process of adding resources to one’s project so as to be able to finish it
faster. It has cost impact.
Fast Tracking, on the
other hand, is the process of performing tasks in parallel so as to be able to
finish the project sooner. It does not have any cost impact, but increases the risks.
Question No.50:
What is the normal productivity
of welder for Carbon steel material per day?
This question is to test your
knowledge of productivity rates. However you
shouldn't memorize
all the answers in your mind, your answer could be "I don’t memorize all
productivity rates since it is vary from an organization to another and from
worker nationality to another. However, i have some standards that I refer to
when the organization productivity rate is not available.
Question No.51:
What is the
difference between free float and total float?
Total float is the
amount of time that an activity can be delayed without delaying the project
completion date. On a critical path, the total float is zero.
Free float is the
amount of time that an activity can be delayed without delaying the Early Start
of its successor activity.
Question No.52:
For an
activity, if the free float is negative whereas the total float is positive. Is
this possible to happen and what's the impact?
It may happen depends
on the activity flow, but that doesn't mean this free float will affect the
completion of the project since the total float is positive.
Define critical
path:
A critical path is
the sequence of project network activities which add up to the longest overall
duration, regardless if that longest duration has float or not. This determines
the shortest time possible to complete the project.
Question No.54:
Does primavera
loads cash in and cash out in same schedule?
Primavera deals with
cost of the project only (cash out) but you can work around with making a resource called cash in/out to view cash in/out
Question No.55:
How to reduce
critical path?
A- Compressing schedule by fast
tracking, crashing, Reduce scope, Cut quality.
B- Fast tracking:
Results in rework, increase risk, requires more attention and communication.
C- Crashing: increase cost,
increase management time
D- Reduce scope:
negative impact on customer satisfaction E- Cut quality: increase risk,
requires good matrices.
Question No.56:
What is the normal
total float allowed for a new project?
Total float should be
not greater than 10% duration of the total project duration. (This percentage
is subjective)
Question No.57:
What are the duties
of a planner?
Assigned in
overall/master schedule, look-ahead targets, and accomplishment reports and
monitoring.
What is Baseline
Program?
An agreed Program
that use to compare the actual result to measure performance of project or
product against what was planned.
Question No.59:
What is SF
dependency? Any example. Have you ever used this?
A logical
relationship in which a successor activity cannot finish until a predecessor
activity has started. Example: The first security
guard shift (successor) cannot finish until
the second
security guard shift
(predecessor) starts.
I don't think I have
ever used this, but I have generally thought of a Start - Finish dependency as
being used where an agree period of handover is required between two activities.
Question No.60:
Are all activities
with negative total float drive the project completion date?
Not all negative
float activities drive the project completion date. Only the chain of
activities driven by their dates and logical relationship drive the completion
date and it is called the longest path.
Question No.61:
What is meant by
recovery schedule?
Recovery schedule is
a revision of the Program's Master Schedule updated on a certain data date. The
Engineer requested the Contractor the recovery schedule to show on how the
contractor he'll be going to recover the incurred delays up-to- date.
Question No.62:
What do you mean by
"EPC", "TIA" & "EOT"?
EPC stands for
"Engineering, Procurement & Construction " TIA = Time Impact
analysis
EOT=
Extension of Time
Question No.63:
How do you get
information to populate and update your schedule?
Organize a planning
workshop with all the Subject matter experts in attendance, plan all your
questions needed for you to make up a plan and schedule. Extract all
information from them, develop a high level initial schedule and populate the
WBS and activity lists. Later on planner should develop forms to be filled by
project team in weekly basis.
Question No.64:
What is the
standard deviation of the activity equal?
standard deviation for activity
is = (Pessimistic duration - Optimistic duration)/6
Question No.65:
Suppose you have a conflict with the project consultant/ owner
representative about a schedule update you have submitted recently. You believe
that you have the right to reflect some time delays in the schedule in favor of
your company, but the owner wouldn't accept that. The conflict escalated and
the consultant hold the monthly payment till you agree on the update according
to his perspective. He's also implicitly threatening to kick you out of the
project unless you are "cooperative". What's should you do?
Unfortunately,
this case is very common in the middle east. The power of consultant is over
estimated, and engineers, especially juniors, will find themselves in similar
situations in one way or another. My answer would be that you should communicate
with your Project Manager immediately. It's not enough to have a casual
conversation during the tea break; you should do that in "WRITTEN"
format only. You should clearly explain the situation; why you think you have
right in your claims; what would be the consequences in case you agree with the
requirements of the consultant; and what are your concerns regarding the
situation. In most of the cases, if the project manager is strong enough, he
will exclude you from direct
contact with the
consultant till he solve the issue; and it might be necessary to consult the
company's lawyer for assistance.
Question No.66:
What does it means
If my free float is positive?
It means I can delay this
activity without delaying the project end date.
Question No.67:
What to look for
when a contractors sends their tender program to be awarded?
Tender schedule is
summarized by natural. However, it should tell the contractor strategy of
excuting the project and the project overall planning.
Question No.68:
What is an S–Curve?
S-curve is a graph
showing cumulative cost or value (measured in terms of money or man-hours)
against time.
Question No.69:
How De-watering
works could affect your schedule?
That based on
calculation of building own weight to be equal to or more the uplift force.
Dewaterwing is required to reduce the uplift force of underground water.
When this force is
less than the weight of building, then dewatering activity could be finished.
Planner should check with the project team when it is recommended to stop the
dewatering and plan accordinglyy. Normaly dewatering will hold the backfilling
and external works around the building.
Question No.70:
Every
project plan has two type of dates, the early start early finish and the late
start late finish. Late start always starts after early start but finish with
the early finish, Why?
Late start denotes the total float
of the activities which allows
the activities in the
early stage of the project to get as late as possible while in the late time of
the project there are mostly critical activities are left which does allow the
late dates to pass over.
Question No.71:
What is the major
difference between Cost variance and Schedule variance?
Schedule
variance=Earned value-Planned value. It is related to the time or data date.
Cost variance=Earned value-Actual cost.
Question No.72:
Why negative
lag/lead is not recommended in a good schedule?
Because other
relationship types can serve the same purpose. For example, instead of using FS relationship with
negative lag, you can use SS relationship with positive lag.
What does variance
in s curve indicate on both axis?
Variance on Y-axis represents the value of (Money, ManHrs., etc.), while X-axis represents time variance.
Question No.74:
What is an open end
activity?
An open ended
activity is an activity that can end at the last day of the project without
delaying the overall projects. An open end activity is normally not followed by
any other activity and its completion can be delayed (within the project life)
in order to focus on more important activities have successors (activities
which can start only at the end of the earlier ones).
Question No.75:
If you
are loading the cost in Primavera, Which cost will you select either in price
in BOQ or your Budget amount or Both?
It depends, if this
schedule is for the consultant, then the budget amount (selling price) should
be loaded. However this is a case where the contractor would like to monitor
the actual cost, in that case actual cost could be loaded. However, cost
control is better in excel than primavera.
What does trend
analysis means?
A trend analysis is
an aspect of technical analysis that tries to predict the future movement of a
stock based on past data.
Question No.77:
A
project shows actual performance is matching the planned performance. The
Project is in delay also. What could be the reason?
The reason is, the
progress is made on the non critical activities than on the critical
activities.
Question No.78:
What are the
difference between flag and milestone activity in primavera?
Mile stone &
flags both are events rather than activities. Some client likes to use flags
rather than mile stone due the following differences.
1. With the use of flags the logic of
main event can be easily tracked as these cannot be created without predecessor
as standalone allocating the constraint. Whereas mile stone can.
2. Flags cannot update manually as
Primavera automatically update the status whereas milestone can be update manually.
3.Flags cannot be constraint only driven by
predecessor whereas milestone can.
Question No.79:
How do you estimate
activities durations?
By generating
meetings & follow ups with contractors and other persons related to
construction, this is also related to the contractual milestones. Normal
activities can be estimated from experience. Special activities can be
estimated by having meetings with project team and experts in this field.
However, the project overall duration is the main constrain that might affect
all other estimations.
What does it mean
if "CPI" greater, lesser or equal to one?
CPI greater than one
means over budget, less than one means under budget & equal to one means
same as per budget.
Question No.81:
What is needed for
a successful project plan?
Contract document,
drawings, B.O.Q as primary & other planning tools as secondary support.
Furthermoe, the involvement of project team in the planning, estimation, and
sequence of work would result more accurate project plan.
Question No.82:
We hire the team in
execution, then who planned for the project?
The planning
of the project is made during the project life cycle with different level of details. For example, during the
tender stage, the tender team is responsible for the high level of planning.
However, when the project is awarded the project team is responsible for the
planning and breakdown.
Question No.83:
How often you
update your Project Baseline ?
It varies from
project to project, depending on reporting/progressing periods. However, the
working schedule should be updated on a continuous basis, as each activity is
started or finished.
What are BCWS,
BCWP, and ACWP?
These three acronyms
are earned value terms that stand for Budgeted Cost for Work Scheduled (planned
value, or PV in the PMBOK Guide’s in my opinion ill-
advised neologisms),
Budgeted Cost for Work Performed (earned value, or EV), and Actual Cost for
Work Performed (actual cost, or AC.)
BCWS is what was budgeted for
each work package as scheduled .
BCWP is the sum of the budgets of
all completed activities/milestones.
ACWP is the sum of
what it actually cost to complete each of the work packages/milestones
Question No.85:
What is a
constraint?
A limitation that reduces the
efficiency with which a project can be accomplished.
Resource availability
is a type of constraint that can delay a project’s schedule and efficiency.
In general,
constraints should not be input to the schedule until after the schedule has
been optimized through critical path analysis.
Question No.86:
What is activity
& What is WBS ?
Activity is a task or
process to be accomplished in a set period of time as part of working toward a
larger project goal. An Activity can be assigned to a resource(s) and have an
associated cost. Activities are ordered with logic links
Work breakdown structure, a
hierarchical format for identifying, displaying,
reporting, and
changing project work. Since the WBS is the “skeleton” of work on which the
resource, cost, schedule information is draped, it is the principle tool for
implementing scope/cost/schedule integration.
What is a
milestone? What are the types of milestone?
A milestone is an
event. Activity-driven milestones are usually entered into PM software as
activities with durations of zero. Since milestones have no duration, once they
are reached they are immediately in the past. It is therefore good practice to
name activities using the past participle of the verb (i.e., “Test component” =
activity; “Component tested” = milestone.
Question-88: What you normally
need to develop a plan?
Answer: I need
the Contract documents to understand the scope, the schedule
drawings to know about areas, Bill of
Quantity-BOQ including cost, scheduling
software
access. Yes, I need to meet my project team to know about a little
productivity rate if I don’t know any specific
activity.
Question-89: What is the
difference between Change order & Variation order Request?
Answer: Technically, there is no such
difference. A change order or Variation request is a change in scope from the
contract but as per contract. If you are curious about which term should be
used, the better refer to your contract documents. I have heard the term Variation
Order but have never seen any documentation for it. Everywhere they write
a Change Order Request.
What is ACWP, BCWP & BCWS?
Answer: These are old acronyms but still efficient to use. These
are the old names of PV, EV, AC, respectively.
- BCWS is
Budgeted Cost of Work Scheduled
- BCWP is
the Budgeted Cost of Work Performed
- ACWP is
Actual Cost of Work Performed
What do you know about DCMA
Scoring?
Answer: DCMA is 14-Point Assessment Metrics to evaluate any
baseline schedule. It includes; 1. Logic 2. Leads 3. Lags 4. Relationship Types
5. Hard Constraints 6. High Float 7. Negative Float 8. High Duration 9. Invalid
Dates 10. Resources 11. Missed Tasks 12. Critical Path Test 13. Critical Path
Length Index (CPLI) 14. Baseline Execution Index (BEI)
What do you about Delay
Analysis Techniques?
Answer: Normally, it is defined in the Contract documents
that how we are going to calculate extension of time, but if not, then there
must be a consensus for using any available technique from both of the parties
like 1) Impacted as planned 2) Windows Analysis 3) Time Impact or 4) As-Built
But-For.
What is the difference between
Planner & a Scheduler?
Answer: Both are quite different but linked to each other
tightly. Somewhere these are just synonyms to each other.
The planner or Planning Engineer reads
the IFC drawings, defines the activities, duration & resources according to site construction conditions. He knows
better all the work phases, even during the tender stage and at the
construction stage. It should be from an engineering background, necessarily.
On
the other hand, the Scheduler takes over the work done already by the planner
to make a more detailed one. This job does not require to have an engineering
background.
What is a different %
complete type in Primavera P6?
Answer: Physical, Units & Duration.
What is the different duration
type in Primavera P6?
Answer: Fixed Units, Fixed Units/time, Fixed Duration &
Units, Fixed Duration & Units/Time.
Differentiate between
budgeted Cost and Budgeted Units?
Answer: Budgeted Cost for an activity is the total budgeted
costs of all resources on that particular activity, whereas Budgeted units are
budgeted units of work for the resource assignment on any specific activity.
Question-44: Differentiate
among WBS, Work Package, and Activity?
Answer: WBS: Work Breakdown Structure- WBS is simply a decomposition
of all the works to complete any project. A WBS is arranged in a hierarchy
having a clear and logical group. A WBS is deliverable-oriented.
Work Package: WP is the lowest level of any work breakdown structure
from which we can manage the cost and duration estimation.
Activity: A discrete, planned portion of work to be performed
in a project.
Why we call Primavera “P6”?
Answer: From 1983 to 2004, Primavera used the P3 suffix for all
kinds of releases like P3 version 1.0, P3 version 3.0, etc., but this suffix
changed to P6 to avoid confusion among P3, SureTrak, and the Primavera. Later
on, P6 is kept as a suffix permanently.
You can read more about different
versions of history here, Primavera P6.
Question 56: What is a CPM
schedule?
Answer: Critical Path Methodology – CPM, or you can name it as a
Critical Path Method, is one of the most popular construction industry
techniques. It uses a mathematical algorithm that helps to find out major
critical jobs on any project schedule.
uestion-54: How to become a
Planning Engineer?
Answer: You must have a relevant degree in Engineering,
then you better start your career by analyzing site work to learn the sequence
of actual work. After that, get some software training like Primavera P6, MS
Project, Asta PowerProjects, Tilos, etc. Prepare plans, practice, and grab the
opportunity you find without considering salary or other perks at the start.
Get some project management training like PMP, Prinace2, etc.
You
can enter this field without an engineering degree, but employers always prefer
to have a project planner with a relevant degree. Hence, you may not fit in
most of the big organizations easily – Better avoid if you are not an engineer.
No comments:
Post a Comment
if you have any doubt please let me know
Note: Only a member of this blog may post a comment.